A change order is a signed document that changes your construction contract’s scope (the work included), cost or timeline. It’s presented before the change happens, and once you and your builder both sign it, it becomes part of your contract.
At Mix & Mesh, I treat every change order as a small contract of its own, because that’s exactly what it is.
This happens in Build It, the stage of the Season Method when your home is under construction and decisions on site count.
At a Glance
- Season: Build It (though one can come up any time after you sign)
- Who’s involved: you and your builder, plus any trade or designer whose work the change touches
- Where it shows up: a change order form, signed by both of you and added to your contract
In this post
- Why Change Orders Matter for Your Build
- How a Change Order Works
- Types of Change Orders
- What a Change Order Looks Like on Paper
- Questions to Ask Your Builder
- Common Change Order Mistakes
- Olivia’s Tip
- Change Order vs. Addendum
- Frequently Asked Questions
Why Change Orders Matter for Your Build
Every change order moves your budget, your timeline, or both. One on its own can feel small, but several add up, and a change made during construction usually costs more than the same choice made during planning.
Change orders can feel scary, but they’re there to protect both of you. They keep everyone on the same page as the project evolves, and they’re also where your contingency gets used.
How a Change Order Works
Something comes up after the contract is signed. You might decide you want a different tub, an inspector might require something new, or the crew might open a wall and find damage nobody could see on the plans.
Before the work moves forward, your builder writes up the change: what’s being added or changed, why, what it costs and how it affects the schedule. You review it, ask questions, and both of you sign and date it. Keep a copy with your project records.
A change order needs both signatures, every time. A verbal yes protects no one, because when the price comes up later, the misunderstanding can go in either direction.
Timing matters too. A change order is a heads-up before something changes, not a bill after the fact. It shouldn’t show up weeks later for work that’s already done, or for a selection you made months ago that has since gone up in price. If change orders tend to arrive late or get saved for the final invoice, raise it with your builder right away, since many changes are time-sensitive.
Types of Change Orders
Unforeseen conditions. Problems nobody could see at the start, like a hidden structural issue, soil that needs a different foundation approach, or a code requirement that wasn’t apparent.
Owner-requested changes. You decide you want something different, like moving a window, adding a built-in, or upgrading a countertop.
Scope gaps and corrections. Something the original estimate should have accounted for, or work that has to be redone. These deserve a closer conversation, because the cost may belong to the original scope rather than being new to you. It isn’t about blame. Plans and estimates leave gaps, and the change order is where you sort out together who covers it.
If a change order doesn’t seem to line up with your original scope, talk it through with your builder first. If you still aren’t confident, an independent inspector can come to your site and review it for you. Treat that as a last resort, since it can make a builder feel second-guessed.
It can settle the question, though. A homeowner I worked with received a change order for unforeseen plumbing, and an independent inspection showed the work should have been part of the original scope. The builder covered the cost.
What a Change Order Looks Like on Paper
| Field | Sample entry |
|---|---|
| Change order number | CO-04 |
| Description | Add a pendant light over the kitchen island |
| Reason | Owner request |
| Cost breakdown | Materials [amount], labor [amount], overhead and fee [amount] |
| Timeline impact | Adds [number] days, no effect on other trades |
| Contract reference | Original contract dated [date] |
| Revised contract total | [amount] |
| Signatures | Homeowner and builder, each with the date |
If any of these pieces is missing from a change order you’re handed, ask for it before you sign.
Questions to Ask Your Builder
- What’s driving this change?
- Can I see labor, materials, overhead and fee separately?
- How many days does this add, and does it affect other trades?
- Is this required for code or structure, or is it optional?
- Are there other ways to handle it that cost less?
Common Change Order Mistakes
- Signing without a cost breakdown, so there’s no way to tell whether the price is reasonable.
- Overlooking the timeline. A change in one room can push back the tile setter, then the painter, then your move-in date.
- Letting small changes pile up without a running total, so the overall budget drifts without anyone noticing.
Olivia’s Tip
Ask, “Is this going to be a change order?” When an issue comes up on site, that one question tells you whether your cost is about to change. A yes means a change order should follow before the work does; a no means the builder is absorbing it.
Change Order vs. Addendum
Both modify your contract. An addendum usually adds to or changes the contract documents themselves, often before work starts, like a revised drawing set or new terms. A change order changes the work, the cost or the schedule once the contract is underway. Some contracts use the two words interchangeably, so check how yours defines each one.
Frequently Asked Questions
Can I say no to a change order?
Yes. You can decline one, especially if it adds work you don’t want or covers something you believe was already in the contract. If the change is required for code or safety, ask your builder what your options are. Either way, put your decision in writing.
Do change orders always cost more?
No. A change order can also be a credit, like when you decide to skip a built-in that was in the original plans.
How long should I take to review a change order?
Long enough to understand it, but try not to sit on it. Trades may be waiting on your answer, so ask your builder when they need a decision.
If a change order has you unsure of your next move, 5 Steps for When It All Goes Wrong is my step-by-step guide for handling problems during construction calmly and in the right order. It comes with The Home Insider, my private group. It’s a monthly membership, and you can cancel anytime.